In March 2020 an agreement for delivering new turbine governors for hydro power plants Doğançay and Yamanli II, Turkey was signed off. The project concerns modernisation of the hydraulic, electro and controlling parts of four Francis turbines in total (Doğançay - TG1 and TG2, power output of each 31 MW, Yamanli II. - TG1 24MW and TG5 13MW). The project is expected to be completed at the end of 2020. The project investor is a major Turkish power company Enerjisa Enerji Üretim A.Ş.